September 8, 2020

Rezoning Application Resubmitted   &

Site Plan Approval (SPA) Application Submitted

Taking into consideration the City and the public’s comments into account, the project team has made refinements to the plans and updated the proposal. Together, these updates constitute our second rezoning application submission and our site plan approval submission to the City.

Project Timeline

We will post any updates here as the project progresses through the development application process.

START

25 January 2019

Meeting with City Staff

Pre-application consultation meeting with City Staff to discuss details of the proposal, including built form, podium design and materiality, the Downtown Plan, as well as the Union Station Heritage Conservation District and design guidelines.

22 March 2019

Meeting with Ward Councillor

Meeting with Councillor Joe Cressy and City Staff to go over the proposal and overall community engagement process.

26 April 2019

Meeting with Toronto Entertainment District BIA

Introductory meeting with the Executive Director of the Toronto Entertainment District BIA to present an overview of the development proposal, the project website and next steps.

10 June 2019

Meeting with TEDRA

Introductory meeting with the Toronto Entertainment District Residents' Association to present an overview of the development proposal and discuss key neighbourhood considerations.

22 August 2019

Application Submission

Submission of our rezoning application to the City of Toronto, which includes a number of plans and reports.

14 November 2019

Preliminary Report Issued

The City issued a Preliminary Report for our rezoning application. This report provides information about our application and outlines a preliminary set of topics for further discussion.

23 January 2020

Community Consultation Meeting

City Staff hosted a Community Consultation Meeting to discuss our proposal. Members of the project team were in attendance to present the proposal, respond to questions and hear feedback.

January - September 2020

Proposal Revisions

The project team reviewed comments and feedback from the City and broader public, and worked on making revisions to the proposal.

8 September 2020

Rezoning Application Resubmission & Site Plan Approval (SPA) Submission

Taking into consideration the City and the public’s comments into account, the project team made refinements to the plans and updated the proposal. Together, these updates constitute our second rezoning application submission and our site plan approval submission to the City.

Currently:

Review of Rezoning Application Resubmission and SPA Submission documents by City Staff.